For builders, civil contractors, developers and project principals, the point is not just that projects may cost more or take longer. Poorly understood risk can flow directly into insurance placement, claims handling and contractual recovery. If ground conditions, design interfaces, approvals risk, latent defects, sequencing constraints or subcontractor dependencies are not properly mapped at the front end, they can later become arguments about policy response, responsibility and causation.

The paper says construction productivity is now below where it was three decades ago and identifies premature project commitments as a major contributor to cost overruns. It also points to the burden created by long and inconsistent procurement frameworks, which can make it harder for contractors to price risk sensibly. From an insurance perspective, that matters because underwriters are increasingly interested in whether a project has a coherent risk allocation model, reliable information and a capable delivery team, rather than simply a headline contract value.

The practical lesson for construction businesses is that insurance should be treated as part of the project design and procurement conversation, not as an administrative task left until mobilisation. Contract works, public liability, delay-related exposures, surety, plant and equipment cover and professional indemnity can all be affected by the way risk is described, transferred and documented in the project contract.

Several issues deserve early attention:

  • whether the contract asks one party to carry risks it cannot realistically control or insure;
  • whether site investigations, design assumptions and approvals pathways are documented clearly enough for underwriting and claims purposes;
  • whether policy limits, deductibles and exclusions align with the project’s actual loss scenarios;
  • whether subcontractor insurance evidence is checked and updated across the life of the works;
  • whether change orders, delay events and defect rectification decisions are recorded in a way that can support a future claim.

The CEDA and WSP recommendations also point towards programmatic procurement, standardised designs and simpler contracting where appropriate. Those reforms would not remove construction risk, but they could make it more visible and more manageable. For insurers, that can improve confidence in the risk. For contractors, it may reduce the chance that a difficult project becomes a dispute over who was supposed to carry an exposure that was never clearly understood.

The limitation is that reform will take time and will depend on government clients, private principals and industry participants changing long-established habits. In the meantime, construction firms may benefit from reviewing how they document risk before tendering, how they explain project controls to insurers and how they estimate construction business insurance costs when contract terms shift more uncertainty onto the delivery chain.

Author: Paige Estritori
Published: Tuesday 17th November, 2026