The ICA says more than 9,000 claims have now been lodged after severe weather affected the two states between 11 and 17 November. Its latest warning focuses on people posing as insurer representatives, seeking upfront cash, offering hail assessments, arranging debris removal or pushing immediate repair contracts that may not be authorised by an insurer. While the release is framed around storm-hit households, the broader message is highly relevant to construction projects: after a weather event, a rushed repair arrangement can complicate evidence, cost control and claims handling.

For projects insured under contract works insurance, the practical issue is usually not just whether there has been damage, but how clearly the damage can be traced, recorded and separated from incomplete work, pre-existing defects or ordinary construction risk. Storms may affect scaffolding, partially installed roofing, wall linings, stored materials, fencing, plant, temporary power and neighbouring property. Each of those exposures may sit under different policy sections, sub-limits or separate policies.

Builders and site managers may wish to keep the following disciplines front of mind after major weather:

  • Make the site safe before detailed inspection, especially where roofing, electrical systems, scaffolding or water ingress is involved.
  • Photograph and video damage before moving materials, removing debris or starting repairs, unless urgent safety action is required.
  • Keep damaged samples where practical, particularly for materials that may later be disputed.
  • Check who has authority to approve emergency works, and whether the insurer, broker, principal or superintendent must be notified first.
  • Record labour, plant, hire, storage and clean-up costs separately from ordinary construction progress costs.

The warning also reinforces why repair governance should be built into project procedures before storm season. A subcontractor, owner, principal or financier may all have an interest in the insured works, but their rights and obligations depend on contracts and policy wording. Where several parties are involved, one person authorising external repair work without checking the insurance process may create later arguments about scope, price or recoverability.

The key lesson is not to delay urgent safety work. It is to avoid letting post-storm urgency erase the evidence trail. A well-managed site damage claim is usually supported by prompt records, clear authority and a careful distinction between emergency protection, permanent reinstatement and unrelated construction costs.

Author: Paige Estritori
Published: Thursday 19th November, 2026